Commissioning Quick-Start Checklist
A one-page overview of the commissioning workflow, with links to the detailed articles. Use it as a field checklist when setting up a new zone.
Read first
Review Cautions & Safety before you begin — including the electrical-safety warning and the one-device-only rule for commissioning.
Before you begin
- Keilton+autani app installed on one device
- Bluetooth 4.2 or later; camera and photo access allowed
- Lighting fixtures installed and powered
- Zones planned per Planning & Sequences of Operations — ≤ 100 devices, < ~150 ft radius, < 9,000 sq ft, avoiding concrete/metal barriers
- Good internet connection available (for cloud sync)
Commissioning steps (at a glance)
- Create a zone — Creating and Managing Zones
- Add lights — Adding Lights; then name them and set rated power
- Configure sensors — Motion and Daylight Harvesting; use Recommended Settings by Space Type as a starting point
- Create groups — Creating Groups, add/remove lights, and set linkage
- Create scenes — Creating Scenes
- Add and program switches — Adding Switches, switch settings, associate scenes/groups
- Set schedules — Creating Schedules
- Speed repetitive setup with templates — Applying Templates
- Save & Force Sync — sync the zone to the cloud (More page) before sharing
- Save / share the QR code — Saving and Sharing QR Codes, only after a successful sync
Large photo-sensor projects (iPad)
For warehouses and other large installs, the Keilton+autani Pro app offers Quick Commission — commission whole groups by pointing the FL30 flashlight at each fixture's sensor.
After commissioning
- Confirm each fixture's status icon (auto/manual/offline).
- Keep firmware current with the Spiral Engineering app if you hit connectivity or feature issues.